Science Interactive Group Knowledgebase

Timeline

Updated on

Spring Term

Task Timing
Start Dates and Tasks loaded
75 days in advance of January start - Beginning of October
Enrollment confirmations begin 75 days in advance of January start - Beginning of October
50% of class start enrollment reviewed 60 days in advance of January start = Mid-November
80% of class start enrollment reviewed 30 days in advance of January start = Mid-December
100% of class start enrollment reviewed 20 days in advance of January start = January 1

Summer Term

Task Timing
Start Dates and Tasks loaded 75 days in advance of May start = Beginning of March
Enrollment confirmations begin 75 days in advance of May start = Beginning of March
50% of class start enrollment reviewed 60 days in advance of May start = End of March
80% of class start enrollment reviewed 30 days in advance of May start = mid-April
100% of class start enrollment reviewed 20 days in advance of May start = end of April

Fall Term

Task Timing
Start Dates and Tasks loaded 75 days in advance of August start = end of May
Enrollment confirmations begin 75 days in advance of August start = end of May
50% of class start enrollment reviewed 60 days in advance of August start = mid-June
80% of class start enrollment reviewed 30 days in advance of August start = mid-July
100% of class start enrollment reviewed 20 days in advance of August start = end of July

0 Comments

Add your comment

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Previous Article Banner Spreadsheet Data Entry
Next Article Course Fee/All Inclusive Course Management